Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field Measurement and Testing Work (Stage 2) Environmental Permit
no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly
Environmental Monitoring & Audit Report
- January 2013 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
February 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory
compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction
Impact due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of Individual Contracts under the
Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/17
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Table 3.5 Summary of submission status under
FEP-02/364/2009
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-01/364/2009
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/18
Table 3.9 Summary of submission status under
FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Table 3.11 Summary of submission status under
FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.13
Summary of submission status under FEP-07/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under
FEP-08/364/2009
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no.
HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no.
HY/2009/18
Table 5.3 Noise Monitoring Station for Contract no
HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no.
HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no.
HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for
Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for
Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no.
HY/2009/18
Table 5.10 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.11 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.12 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no.
HY/2009/19
Table 5.15 Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no.
HK/2009/02
Table 5.17 Details of Waste Disposal for Contract no.
HY/2009/18
Table 5.18 Details of Waste Disposal for Contract no.
HY/2009/15
Table 5.19 Details of Waste
Disposal for Contract no. HY/2009/19
Table 5.20 Details of Waste Disposal for Contract no.
HK/2010/06
Table 8.1 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for
Contract no. HY/2009/19
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix
5.2 Noise
Monitoring Results and Graphical Presentations
Appendix
5.3 Air
Quality Monitoring Results and Graphical
Presentations
Appendix 5.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
¡P
Backfilling works on top of SCL protection works
¡P
Pre-bored H piling works for the proposed CWB.
¡P
Pre-drilling works for CWB (Stage 2)
¡P
Ground treatment works for proposed CWB diaphragm wall.
¡P
Plant Mobilization for diaphragm wall construction works at Stage 2.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
¡P
Placing concrete of the final portion for precast scission seawall 2X
¡P
Trimming of pile head at WCR1 of Tunnel Portion 1
¡P
Blinding laying construction at WCR1 of Tunnel Portion 1
¡P
Waterproofing installation at WCR1 of Tunnel Portion 1 Bay 1 - Bay 7
¡P
Rebar fixing for base slab.
¡P
Backfilling of temporary sheet pile seawall
¡P
Extraction of total 150 nos. of western temporary sheet piling.
¡P
Casting of Diaphragm wall of panel P106, C107, P108, C109, P110, C111,
P112, C113, P114, C115 & P116. Total 11 out of 19 D-wall panels were
completed.
¡P
Panel BHP3 and BHP7 in Zone 3.
¡P
Trial excavation, Footpath Set back, UU Diversion and preparation works
for Hung Hing Road Flyover Diversion Stage 1.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
Excavation and Lateral Support works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of diaphragm at TS2
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile cap & column (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Post
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
¡P
Utility works in section 2
Noise
Monitoring
Air Monitoring
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Contract
no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Removal of remaining guide wall along
¡P
Backfilling at SCL section to the required level.
¡P
Installation of pre-bored H-pile in CWB Stage 1b (from Ch80 to Ch120).
¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220).
¡P
CWB diaphragm wall construction under the atrium link.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Blinding for the base slab construction and waterproofing installation
at tunnel portion 1.
¡P
Rebar fixing fro the base slab construction at Tunnel Portion 1.
¡P
Base slab concreting at Tunnel Portion 1.
¡P
G.I. and remove the temporary sheetpile wall at WCR2
¡P
Diaphragm wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
¡P
Bulkhead at Bay 14 of Box Culvert ¡§O¡¨ and stage 2 diversion of uncharted
drainage works at Box culvert ¡§O¡¨.
¡P
Preparation work for Bored Pile construction of EP01 ¡V EP11 at Tunnel Portion 3&4.
¡P
Trial excavation, footpath set back, UU diversion, reprovision of street
furniture and preparation works for Hung Hing Road Diversion Stage 1
¡P
Curing of caisson seawall precast unit 2X and protective coating on
flat-top barge.
¡P
Construction of 1800 connection of Box Culvert N1, Bay 4 & Bay 5 and
FRP installation at WCR1 area.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Pos
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/B and
Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009,
FEP-03/364/2009,
FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and ¡§Environmental
Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no.
EP-364/2009/B, Further Environmental Permit (FEP) nos. FEP-01-364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A,
FEP-07/364/2009/A and FEP-08/364/2009/A during
the period Dec 2012 to Jan 2013. The
cut-off date of reporting is at 27th of each reporting month
Section 1 Introduction ¡V details the scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit ¡V summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ¡V summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ¡V summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and
¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called
¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested
2.2.1.
Design and Construction of Central ¡V Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai
Bypass (CWB) and
Island Eastern Corridor Link (IECL) includes:
¡P
A
dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
¡P
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
¡P
Tunnel
control buildings and ventilation buildings;
¡P
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
¡P
Associated
road lighting, road signing, traffic control and surveillance system; and
¡P
Other
associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912
3010 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566 7522 |
Contractor¡¦s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214
7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214 7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor¡¦s
Representative |
Mr. David Lau |
3557
6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee
Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Clement Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3. In this
reporting month, the principal work activities of individual contracts are
included as follows:
Contract no.
HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Backfilling works on top of SCL protection works
¡P
Pre-bored H piling works for the proposed CWB.
¡P
Pre-drilling works for CWB (Stage 2)
¡P
Ground treatment works for proposed CWB diaphragm wall.
¡P
Plant Mobilization for diaphragm wall construction works at Stage 2.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Placing concrete of the final portion for precast scission seawall 2X
¡P
Trimming of pile head at WCR1 of Tunnel Portion 1
¡P
Blinding laying construction at WCR1 of Tunnel Portion 1
¡P
Waterproofing installation at WCR1 of Tunnel Portion 1 Bay 1 - Bay 7
¡P
Rebar fixing for base slab.
¡P
Backfilling of temporary sheet pile seawall
¡P
Extraction of total 150 nos. of western temporary sheet piling.
¡P
Casting of Diaphragm wall of panel P106, C107, P108, C109, P110, C111,
P112, C113, P114, C115 & P116. Total 11 out of 19 D-wall panels were
completed.
¡P
Panel BHP3 and BHP7 in Zone 3.
¡P
Trial excavation, Footpath Set back, UU Diversion and preparation works
for Hung Hing Road Flyover Diversion Stage 1.
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (
¡P
Excavation and Lateral Support works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of diaphragm at TS2
Contract no. HY/2009/19 ¡V Central ¡V
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile cap & column (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Post
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
2.4.4.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
¡P
No further work under designated project1
1Remarks: The construction of bored pile
E3B under FEP-03/364/2009 was confirmed completed and the bored pile E3B and
the works area was handover
to contract no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
¡P
Excavation of trial pit
¡P
Transplanting of trees
¡P
Hoarding erection and modification
¡P
Installation of couplers, UU detection, trial trench, pre-drilling
¡P
Excavation
¡P
Sheet Piling
¡P
Drainage works
¡P
Tunnel works
¡P
Trough structure construction and associated drilling and grouting
¡P
Road works
¡P
OHVD installation
¡P
Cooling main bridge construction
¡P
Pre-bored H-piling
¡P
Bridge construction
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
¡P
Removal of remaining guide wall along
¡P
Backfilling at SCL section to the required level.
¡P
Installation of pre-bored H-pile in CWB Stage 1b (from Ch80 to Ch120).
¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220).
¡P
CWB diaphragm wall construction under the atrium link.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
¡P
Blinding for the base slab construction and waterproofing installation
at tunnel portion 1.
¡P
Rebar fixing fro the base slab construction at Tunnel Portion 1.
¡P
Base slab concreting at Tunnel Portion 1.
¡P
G.I. and remove the temporary sheetpile wall at WCR2
¡P
Diaphragm wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
¡P
Bulkhead at Bay 14 of Box Culvert ¡§O¡¨ and stage 2 diversion of uncharted
drainage works at Box culvert ¡§O¡¨.
¡P
Preparation work for Bored Pile construction of EP01 ¡V EP11 at Tunnel Portion 3&4.
¡P
Trial excavation, footpath set back, UU diversion, reprovision of street
furniture and preparation works for Hung Hing Road Diversion Stage 1
¡P
Curing of caisson seawall precast unit 2X and protective coating on
flat-top barge.
¡P
Construction of 1800 connection of Box Culvert N1, Bay 4 & Bay 5 and
FRP installation at WCR1 area.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
¡P
ELS works at TS4
¡P
Rock breaking works at TPCWAE
¡P
Tunnel works at TS1
¡P
Horizontal drilling for mined tunnel
¡P
Pipe roofing installation
¡P
Construction of Diaphragm Wall at TS2
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Pos
¡P
Construction of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai
Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the current status on licences
and/or permits on environmental protection pertinent and
submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul
2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul
2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 ¡V 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13
July 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7010400 |
16
Mar 2010 |
N/A |
Valid |
Contract no. 04/HY/2006 ¡V
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at
3.1.5. Summary of the current status on
licences and/or permits on environmental protection pertinent and
submission under FEP-02/364/2009 for contract no.
HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling equipment |
GW-RS-1293-12 |
10 Dec
2012 |
10 Dec
2012 to 9 June 2013 |
Valid |
GW-RS0760-12 |
16 Jul
2012 |
20 Jul
2012 to 19 Jan 2013 |
Expired |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03
Feb 2013 |
Cancelled |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Cancelled |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01
Feb 2013 |
Cancelled |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012
to 9 Feb 2013 |
Cancelled |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27
Feb 2013 |
Cancelled |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15
Mar 2013 |
Cancelled |
|
GW-RS-0052-13 |
18 Jan
2013 |
20 Jan
2013 to 19 July 2013 |
Valid |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29
Mar 2013 |
Cancelled |
|
GW-RS1017-12 |
27 Sep
2012 |
30 Sep
2012 to 24 Mar 2013 |
Valid |
|
GW-RS0793-12 |
21 Sep
2012 |
30 Sep
2012 to 29 Mar 2013 |
Valid |
|
GW-RS1040-12 |
8 Oct
2012 |
13 Oct
2012 to 12 Apr 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov
2012 |
17 Nov
2012 to10 May 2013 |
Valid |
|
GW-RS1184
-12 |
15 Nov
2012 |
17 Nov
2012 to 8 May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov
2012 |
21 Nov
2012 to 8 May 2013 |
Valid |
|
GW-RS1179-12 |
20 Nov
2012 |
22 Nov
2012 to 21 May 2013 |
Valid |
|
GW-RS1187-12 |
20 Nov
2012 |
27 Nov
2012 to 26 May 2013 |
Valid |
|
GW-RS1199-12 |
20 Nov
2012 |
26 Nov
2012 to 25 May 2013 |
Valid |
|
Discharge Licence |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
20 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr
2013 |
Valid |
GW-RS1069-12 |
17 Oct 2012 |
19 Oct 2012 to 18 Apr
2013 |
Valid |
|
GW-RS1076-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1204-12 |
9 Nov 2012 |
29 Nov 2012 to 23 May 2013 |
Valid |
|
GW-RS1272-12 |
5 Dec 2012 |
5 Dec 2012 to 26 May 2013 |
Valid |
|
GW-RS1223-12 |
27 Nov 2012 |
7 Dec 2012 to 5 June 2013 |
Valid |
|
GW-RS1243-12 |
3 Dec 2012 |
5 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RE1055-12 |
30 Nov 2012 |
3 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RS1228-12 |
30 Nov 2012 |
30 Nov 2012 to 29 May 2013 |
Valid |
|
GW-RS1245-12 |
5 Dec 2012 |
6 Dec 2012 to 5 May 2013 |
Valid |
|
GW-RS1363-12 |
24 Dec 2012 |
9 Jan 2013 to 7 July 2013 |
Valid |
|
GW-RS1381-12 |
31 Dec
2012 |
9 Jan 2013 to 7 July 2013 |
Valid |
|
Gw-RS1384-12 |
31 Dec
2012 |
17 Jan 2013 to 16 July 2013 |
Valid |
|
GW-RS0671-12 |
25 Jun
2012 |
17 Jul 2012 to 16 Jan 2013 |
Valid |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0061-13 |
17 Jan 2013 |
1 Feb 2013 to 31 July 2013 |
Valid |
|
GW-RS0062-13 |
17 Jan 2013 |
21 Jan 2013 to 15 July 2013 |
Valid |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
|
GW-RS0996-12 |
25 Sept 2012 |
26 Sept 2012 to 25 Mar 2013 |
Valid |
|
GW-RS1084-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1086-12 |
25 Oct 2012 |
28 Oct 2012 to 16 Apr 2013 |
Valid |
|
GW-RS1174-12 |
9 Nov 2012 |
11 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1158-12 |
16 Nov 2012 |
18 Nov 2012 to 16 May 2013 |
Valid |
|
GW-RS1167-12 |
16 Nov 2012 |
23 Nov 2012 to 21 May 2013 |
Valid |
|
Discharge
Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under FEP-01/364/2009
EP
Condition |
Submission |
Date of Submission |
Condition
2.7 and 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Condition
2.6 |
Environmental Management
Organization Chart |
14 Jun
2011 |
Condition
2.6 |
Commencement Date of Works |
21 Jun
2011 |
Condition 2.11 |
Landscape
Plan (Revision B) |
20 Nov 2012 |
Condition
2.9 |
Noise
Management Plan (Revision A) |
13 Jan 2012 |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and Permits
under Contract no. HY/2009/18
Permit / Licence / Notification
/ Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0769-12 |
23 Jul 2012 |
25 Jul 2012 ¡V |
Valid |
GW-RS0833-12 |
09 Aug 2012 |
09 Aug 2012 ¡V |
Valid |
|
GW-RS0925-12 |
31 Aug 2012 |
3 Sep 2012 ¡V |
Cancelled |
|
GW-RS1208-12 |
23 Nov 2012 |
26 Nov 2012- 31 Mar 2013 |
Valid |
|
GW-RS1382-12 |
02 Jan 2013 |
04 Jan 2013 to 30 Jun 2013 |
Valid |
|
GW-RS0068-13 |
18 Jan 2013 |
05 Feb 2013 to 03 Aug 2013 |
Valid |
|
GW-RS0036-13 |
11 Jan 2013 |
23 Jan 2013 to 22 Jul 2013 |
Valid |
|
GW-RS1286-12 |
07 Dec 2012 |
11 Dec 2012- 05 Jun 2013 |
Valid |
|
Discharge Licence |
WT00012998-2012 |
25 May 2012 |
31 Jan 2016 |
Valid |
WT00012967-2012 |
17 Sep 2012 |
30 Sep 2017 |
Valid |
|
WT00014966-2013 |
08 Jan 2013 |
31 Jan
2018 |
Valid |
|
Registration as a Waste Producer |
WPN:
8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Registration
completed |
Billing
Account under Waste Disposal Ordinance (Land) |
Account
No.: 7011587 |
11 Oct 2010 |
Account
approved |
Valid |
Table 3.9 Summary of submission status under
FEP-05/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition
2.9 |
Noise
Management Plan |
01
March 2011 |
Condition
2.10 |
Landscape
Plan (Rev. 5) |
12
March 2012 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
3.1.8.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for bored
pile construction at Eastern Breakwater of CBTS |
GW-RS1009-12 |
03 Oct 2012 |
03 Oct 2012 to 25 Mar 2013 |
Valid |
Construction
Noise Permit (CNP) for
non-piling equipment |
GW-RS1153-12 |
15 Nov 2012 |
15 Nov 2012 to 06 May 2013 |
Valid |
GW-RS1191-12 |
26 Nov 2012 |
26 Nov 2012 to 11 May 2013 |
Valid |
|
GW-RS0038-13 |
17 Jan 2013 |
26 Jan 2013 to 25 Jul
2013 |
Valid |
|
GW-RS0087-13 |
24 Jan 2013 |
26 Jan 2013 to 20 July 2013 |
Valid |
|
GW-RS1250-12 |
30 Nov 2013 |
1 Dec 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0789-12 |
27 Jul
2012 |
1 Aug
2012 to 25 Jan
2013 |
Valid |
|
GW-RS0984-12 |
21 Sep
2012 |
23 Sep
2012 to 22 Mar
2013 |
Valid |
|
GW-RS1345-12 |
21 Dec 12 |
24 Dec 12 to 23 Jun 2013 |
Cancelled |
|
GW-RS1342-12 |
21 Dec 2012 |
26 Dec 2012 to 25 Jun 2013 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27
Sep 2010 to 27
Jan 2016 |
Valid |
Billing Account under Waste
Disposal Ordinance (Dumping by Vessel) |
7011761 |
10 Jul 2012 |
17
Oct
2012 to 16
Jan
2012 |
Valid |
Water Discharge License (TS1) |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011 to 31 Mar 2016 |
Valid |
Water Discharge License
(Discharge at CHT area) |
WT00012941-2012 |
10 May 2012 |
10 May 2012 to 31 May 2014 |
Valid |
Water Discharge License
(Discharge at TPCWAE) |
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011 to 31 Dec 2013 |
Valid |
Water Discharge License
(Discharge at TS4) |
WT00011718-2012 |
16 Jan 2012 |
16 Jan 2012 to 31 Jan 2014 |
Valid |
Water Discharge License
(Discharge at TS2 |
WT00014974-2013 |
10 Jan 2013 |
10 Jan 2013 to 31 Jan
2015 |
Valid |
Table 3.11 Summary of submission status under FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works Schedule |
15 Mar
2011 |
Condition
2.8 |
Location
Plan |
15 Mar
2011 |
Condition
2.23 |
Noise
Management Plan |
6 May
2011 |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9. The current status on licences and/or
permits on environmental protection pertinent and
submission under FEP-07/364/2009/A for contract no.
HY/2009/19 are shown in Table 3.12 and Table
3.13.
Table 3.12 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction
Noise Permit (CNP) |
GW-RS1230-12
|
28 Nov
2012 |
28 Nov
12 to 25 May 13 |
Valid |
GW-RS0013-13 |
08 Jan
2013 |
07 Jul
2013 |
Valid |
|
GW-RS1065-12 |
16-Oct-12 |
20-Oct-12 to 20-Apr-13 |
Valid |
|
GW-RS0871-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
|
GW-RS0885-12 |
27-Aug-12 |
26-Feb-13 |
Cancelled |
|
GW-RS0046-13 |
18 Jan 2013 |
10 Jul 2013 |
Valid |
|
GW-RS0953-12 |
17-Sep-12 |
21-Sep-12 to 20-Mar-13 |
Cancelled |
|
GW-RS1210-12
|
29-Nov-12 |
29 Nov 12 to 28 May 13 |
Cancelled |
|
Water Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Cancelled |
|
WT00010093-2011 |
17-Aug-12 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table
3.13
Summary
of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date
of Submission |
Condition 2.9 |
Noise Management Plan |
02 Jun 2011 |
Condition 2.13 |
Landscape Plan |
16 March 2012 |
Condition 2.9 |
Noise Management Plan (Rev.2) |
28 October 2011 |
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
3.1.10.
The current status on licences and/or permits on environmental protection
pertinent and submission under FEP-08/364/2009/A for contract no. HK/2010/06 showed in Table 3.14 and Table 3.15.
Table 3.14 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-08/364/2009/A |
15
June 2012 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS0923-12 |
31 Aug
2012 |
15 Oct 2012 ¡V 14 Apr 2013 |
Valid |
Table 3.15 Summary of submission status under
FEP-08/364/2009
EP
Condition |
Submission |
Date of Submission |
|
Acknowledgement
letter of FEP-08/364/2009A |
14
Aug 2012 |
Condition
2.9 |
Noise
Management Plan |
26 Nov 2012 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit
Levels for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
4.1.2.
Review of feasibility on the real time noise
monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan
fireboat Station was found not appropriate to be a monitoring station for
monitoring the IECL Piling works and Demolition after visited.
4.1.3.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu |
Tin Hau |
RTN4 |
|
Noise
Monitoring Parameters, Frequency and Duration
4.1.4. The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
4.1.5. Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
¡P
One
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.6. Real time
noise shall be carried out at the designated monitoring stations. The following
is an initial guide on the regular monitoring frequency for each station on a
24 hours daily basis when noise generating activities are underway:
¡P
One
set of measurements between 0700 and 1900 hours on normal weekdays.
¡P
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
¡P
One
set of measurements between 2300 and 0700 hours on next day on everyday.
4.1.7. If
construction works are extended to include works during the hours of 1900 ¡V 0700
as well as public holidays and Sundays, additional weekly impact monitoring
shall be carried out during respective restricted hours periods. Applicable
permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.8. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.9. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
4.1.10. The sound
level meter shall be checked using an acoustic calibrator generating a known
sound pressure level at a known frequency before deployment to the site and
during each site visit. Measurements will be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air monitoring stations for the Project
are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community Liaison
Centre |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
Remarks: As per
the ENPC meeting in March 2011, the monitoring stations CMA3a ¡V Future CWB site
office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
¡P
0.6 ¡V 1.7 m3 per minute adjustable flow range;
¡P
Equipped with a timing / control device with +/- 5 minutes accuracy for
24 hours operation;
¡P
Installed with elapsed-time meter with +/- 2 minutes accuracy for 24
hours operation;
¡P
Capable of providing a minimum exposed area of 406 cm2;
¡P
Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
Equipped with a shelter to protect the filter and sampler;
¡P
Incorporated with an electronic mass flow rate controller or other
equivalent devices;
¡P
Equipped with a flow recorder for continuous monitoring;
¡P
Provided with a peaked roof inlet;
¡P
Incorporated with a manometer;
¡P
Able to hold and seal the filter paper to the sampler housing at
horizontal position;
¡P
Easily changeable filter; and
¡P
Capable of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory
Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8¡¨ x 10¡¨ shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of
equipments are presented in Appendix
4.2.
5.0.1. The
environmental monitoring will be implemented based on the division of works
areas of each designated project managed under different contracts with
separate FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2. In the
reporting month, the concurrent contracts are as follows:
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
Contract
no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
Contract
no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link under
FEP-07/364/2009
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Contract
no. HK/2009/02 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass at
Wan Chai East
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central - Wan Chai Bypass over
MTR Tsuen Wan Line
5.0.3. The
environment monitoring schedules for reporting month and coming month are presented
in Appendix
5.1.
5.1.1. Monitoring for
report of review baseline noise level was performed from 11 April 2011 to 8
June 2011. Then the report was
submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved
by ER by January 2012. The new
baseline is used for the noise calculation of this reporting month starting
from January 2012.
Contract no. HY/2009/17 ¡VCentral ¡V Wan
Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced piling works under
FEP-03/364/2009
5.1.2. The proposed
division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table
5.1 Noise Monitoring Stations
for
Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.3. No action or
limit level exceedance was recorded during daytime period in the reporting
month.
5.1.4. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/18 ¡V Central ¡V Wan
Chai Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.1.5. Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.2 below:
Table
5.2
Noise Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark:
M7e has become a reference station starting from 7 Aug 2012
5.1.6. No action or
limit level exceedance was recorded during daytime period in the reporting
month.
5.1.7. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix
5.2.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre ¡V Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 ¡V Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
5.1.8. The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on
26 April 2011. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.9. 1 limit exceedance was recorded on 24
Jan 2014 at M1a-Habour Road Sports Centre.
5.1.10. Non-CWB project
drilling works nearby was observed during noise monitoring and considered as
the major noise contribution. As
such, the exceedance was not related to the Project.
5.1.11. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix
5.2.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
5.1.12. The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.4 below.
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.13. No action or
limit level exceedance was recorded in this reporting month.
5.1.14. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix
5.2.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
5.1.15. Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table
5.5 below.
Table 5.5 Noise
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.16. Four limit level exceedances were recorded on 3,8,15
and January 2013 at M6 ¡V
HK Baptist Church Henrietta Secondary School in the reporting month.
5.1.17. Major
traffic noise observed during monitoring was considered as the major noise contribution.
As such, the limit level exceedances were concluded as non-project related.
5.1.18. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
5.2.1.
As confirmed by CWB RSS, the IECL parapet removal operations and associated
construction work will commence in January 2013. Liaison was conducted with HK Baptist Church Henrietta Secondary School,
Po Leung Kuk Yu Lee Mo Fan Memorial School and Causeway Bay Community Centre regarding
the set up of RTN3 real time noise monitoring station.
5.2.2.
5.2.3.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013.
5.2.4.
Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up
on 4 Sep 2012 and station set up was performed on 14 Sep 2012. Real time noise
baseline capturing was conducted during time period without construction work
from 21 Sep 2012 to 04 Oct 2012.
5.2.5.
Real time noise monitoring at RTN3 ¡V Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced
since 06 Oct 2012.
5.2.6.
Oil Street Community Liaison Centre was confirmed to be demolished in
mid-October by CWB RSS. This
presented a need for relocation of RTN2 ¡V Oil Street Community Liaison
Centre. After liaison with Hong
Kong Electric, permission was granted on 21 Sep 2012 for real time noise
monitoring set up at City Garden Electric Centre (RTN2a ¡V Electric Centre),
which is a representative of the noise sensitive receiver City Garden.
5.2.7.
RTN2 previously located at oil Street Community Liaison Centre was
relocated to Hong Kong Electric Centre on 5 Oct 2012, which is a representative
of the noise sensitive
Contract no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009 and
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under FEP-07/364/2009/A
Table
5.6 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.9.
Limit level Exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 3 Jan 2013 and 16 Jan
2013. After checking with contractor, no noisy activities were undertaken
during monitoring and exceedances were contributed by no designated project
works and nearby IEC traffic. As such, the exceedances were concluded as non
project related.
5.2.10.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix 5.4 .
5.2.11.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table
5.7 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu |
RTN4 |
Tin Hau
|
|
* Real time noise
monitoring results and graphical presentation during night time period are for
information only.
** Real time
noise monitoring results and graphical presentation of RTN3 and RTN4 are for
reference as the demolition work at the IECL has not commenced.
5.2.12.
Limit level Exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 3 Jan 2013 and 16 Jan
2013. After checking with contractor, no noisy activities were undertaken
during monitoring and exceedances were contributed by no designated project
works and nearby IEC traffic. As such, the exceedances were concluded as non
project related.
5.2.13.
No action and limit level exceedance was
recorded at RTN2a-Electric Centre during the reporting month.
5.2.14.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.4.
5.3.1
Due to extension of site boundary by
contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street
Community Liaison Centre has been finely adjusted on 21 April 2012.
Contract
no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
5.3.2 The
proposed division of air monitoring stations are summarized in Table 5.8
below. Air monitoring for the piling works under contract no. HY/2009/17 was
commenced on 8 October 2010.
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA1b |
Oil Street
Community Liaison Centre |
CMA2a |
|
5.3.3 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai
Bypass (CWB) ¡V Central Interchange under FEP-05/364/2009/A
5.3.4 Air
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 21 April 2011. The proposed division of air monitoring stations
are summarized in Table 5.9 below.
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.5 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
5.3.6 The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on
25 August 2011. The proposed division of air monitoring stations are summarized
in Table 5.10 below.
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
5.3.7 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.3.8 The
commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on
26 April 2011. The proposed division of air monitoring stations are summarized
in Table 5.11 below.
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.9 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract
no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
5.3.10
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air
quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table
5.12 below.
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.11 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
5.3.12 The
proposed division of air monitoring stations are summarized in Table 5.13
below. Air monitoring for the tunnel works under contract no. HY/2009/19 was
commenced on 26 April 2011.
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
5.3.13 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract no.
HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works under FEP-03/364/2009
5.4.1. No Inert
and non-inert C&D wastes were disposed in the reporting month. Details of
the waste flow table are summarized in Table 5.14
Table 5.14 Details
of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIl |
Nil |
CWBP / TKO137 |
Inert C&D materials recycled |
Nil |
1354.82 |
SENT |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
5.4.2. No Inert C&D wastes were recycled
and non-inert C&D wastes were disposed of in this reporting month. Details
of the waste flow table are summarized in Table 5.15.
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed |
Nil |
22249.345 |
TKO137, TM38 |
Inert C&D materials recycled |
Nil |
5104.5 |
N/A |
Non-inert C&D materials disposed |
47.8 |
1163.88 |
SENT Landfill |
Non-inert C&D materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
250 |
8900 |
N/A |
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.4.3. Inert
C&D & non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.16.
Table 5.16 Details of Waste Disposal for
Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
2571.8 |
227871.18 |
TKO137 / TM 38 |
N/A |
Inert C&D materials recycled, m3 |
0 |
18161 |
n/a |
N/A |
Non-inert C&D materials disposed, m3 |
39.68 |
785.59 |
SENT Landfill |
N/A |
Non-inert C&D materials recycled, m3 |
N/A |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
350 |
6571 |
SENT Landfill |
N/A |
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
5.4.4. Inert
C&D and non-inert C&D waste was disposed of in this reporting month.
Details of the waste flow table are summarized in Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HY/2009/18
11477 |
82433 |
||
8814 |
47701 |
||
71 |
865 |
||
73.21 |
|||
3565 |
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
5.4.5. Inert & Non-inert C&D wastes
were disposed of in this reporting month. Details
of the waste flow table are summarized in Table 5.18.
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month(m3) |
Cumulative Quantity-to-Date(m3) |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
27771.4 3714.7 |
214226.3 154308.4 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials recycled, m3 |
2805.8 |
206160.4 |
HY/2009/11 ex-PCWA TS4 TS2 |
Non-inert C&D materials disposed, m3 |
35.9 |
623 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
8.4 |
542659.4 kg |
Xun Xiang Metalware Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
12,051 |
Dunwell Group |
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.6. Inert and
Non-inert C&D wastes were disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed |
23051.2 |
246515.89 |
N/A |
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
39.72 |
714.05 |
SENT Landfill |
Non-inert
C&D materials recycled |
Nil |
N/A |
|
Chemical waste
disposed |
N/A |
Contract
no. HK/2010/06 Wan Chai Development Phase II - Central-Wan Chai Bypass over MTR
Tsuen Wan Line under FEP-08/364/2009/A
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
6.0.1. The Event
Action Plan for construction noise, air qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 ¡VCentral ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
6.1.1. No
exceedance was recorded in the reporting month.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass (CWB) ¡V Central
Interchange under FEP-05/364/2009/A
6.1.2. No exceedance
was recorded in the reporting month.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
6.1.3. One limit level
exceedance was recorded on 24 Jan 2013 at M1a- Habour Road Sports Centre in the
reporting month. Investigation found that non- CWB project drilling works
nearby was the major noise contribution during monitoring. As such the
exceedance was not related to the Project.
Contract
no. HK/2009/02 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.4. One limit level
exceedance was recorded on 24 Jan 2013 at M1a- Habour Road Sports Centre in the
reporting month. Investigation found that non- CWB project drilling works
nearby was the major noise contribution during monitoring. As such the
exceedance was not related to the Project.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V Tunnel (
6.1.5. No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.6.
Four limit level
exceedances were recorded on 3, 8, 15 and 24 January 2013 at M6 ¡V HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that major traffic
noise was contributed in the noise monitoring and exceedances were not
related to the Project.
Real Time Noise Monitoring
Contract
no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V
Advanced piling works under FEP-03/364/2009
6.1.7. Non project
related exceedances were recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot on 3 Jan 2013 and 16 Jan 2013. Investigation found that exceedances
were contributed by non designated project works and nearby IEC traffic.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Contract no. HY/2009/17 ¡V Central ¡V Wan Chai Bypass
(CWB) at FEHD Whitfield Depot ¡V Advanced piling works under FEP-03/364/2009
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/18 ¡V Central ¡V Wan Chai Bypass
(CWB) ¡V Central Interchange under FEP-05/364/2009/A
6.2.2.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at
6.2.3.
No exceedance was recorded in the reporting month.
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.2.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
6.2.5.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceedance was recorded in the reporting
month.
6.3.1.
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.3.2.
No project-related non-compliance from
monitoring was recorded in the reporting month.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/B, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Monthly EM&A report (December
2012) of Central Reclamation Phase III (CRIII), filling works, road works, building
construction works and pipe works were performed in the December 2012 reporting
month. The water quality monitoring was completed in October 2011 and no Project-related
exceedance was recorded for air and noise monitoring. It can be concluded that cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai
Development Phase II was marine works at HKCEC areas, cross-harbour Watermains,
Fresh Watermains and Cooling Watermains Installations, tunnel works at Wan Chai
East, ELS work at TS4 and deep excavation at TPCWAE
TCBR1W. Excavation of trial pit at Central Interchange, and marine pilling and
box culvert construction at North Point area. The major environmental impact
was water quality impact at
7.0.4.
The major environmental impacts generated
from excavation at Central and tunnel works at Wan Chai East, IECL and Causeway
Bay Typhoon Shelter were undertaken in the reporting month. No significant air
impact was anticipated in the reporting month. Besides, no project-related
exceedances were recorded during the environmental monitoring events in the reporting
month. Thus, it is evaluated that
the cumulative construction impact from the concurrent projects including Wan
Chai Development Phase II was insignificant.
8.0.1. During
this reporting month, weekly environmental site audits were conducted for Contracts
no. HY/2009/15, HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and HK/2010/06.
No non-conformance was identified during the site audits. Construction of bored pile E3B under
HY/2009/17 was confirmed completed and the respective work area under FEP was
inspected under HY/2009/19 from 19 Dec 2012 onwards. The Contractors rectified
major observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
8.0.2.
Four site inspections for Contract no.
HY/2009/15 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary of Environmental Inspections
for Contract no. HY/2009/15
Date |
Item |
Observations |
Action taken by Contractor |
Outcome |
130103_02 |
3-Jan-13 |
Drip trays should be provided to oil buckets |
Oil buckets were removed. |
Completion as observed on 08 Jan 2013 |
130103_03 |
3-Jan-13 |
Muddy bloom generation was observed at TS1 area neat TZ1 during
marine vessel passage |
No muddy bloom was observed |
Completion as observed on 08 Jan 2013 |
130108_02 |
8-Jan-13 |
Oil stain should be cleared and removed as chemical
waste.(Eastern breakwater, Eastern breakwater landing step) |
Oil stains were removed. |
Completion as observed on 15 Jan 2013 |
130108_03 |
8-Jan-13 |
Milky discharge observed at treatment plant outfall (Ex-pcwa) |
No milky discharge was observed |
Completion as observed on 15 Jan 2013. |
130115_04 |
15-Jan-13 |
Oil stain should be cleared and removed as chemical
waste.(Eastern breakwater, Eastern breakwater landing step) |
Oil stains were removed |
Completion as observed on 22 Jan 2013. |
130122_01 |
22-Jan-13 |
The embankment of the temporary perimeter drainage channel should
be reinstated. |
The embankment of perimeter has been reinstated |
Completion as observed on 28 Jan 2013. |
8.0.3.
Four site inspections for Contract no.
HY/2009/18 was carried out during this reporting period. No observation is found in the reporting
month.
8.0.4.
Five site inspections for Contract no.
HY/2009/19 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.2
Table 8.2 Summary of Environmental Inspections
for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
121228_03 |
28-Dec-12 |
Sandbag or other protective measures should be provided at marine
work platform to prevent overflow of muddy water |
Protective measures were provided for marine work platform |
Completion as observed on 09 Jan 2013 |
130116_03 |
16-Jan-13 |
Damaged silt curtain should be replaced to avoid gaps. |
Silt curtain was replaced. |
Completion as observed on 23 Jan 2013 |
130123_01 |
23-Jan-13 |
Muddy water was observed discharged from wastewater treatment
outlet point and muddy dispersion was observed outside silt curtain enclosure.
(Culvert T outfall) |
Wastewater treatment plant operates in order and silt curtain was
tightened |
Completion as observed
on 30 Jan 2013 |
130123_02 |
23-Jan-13 |
Overflow of muddy water from site boundary was observed. Reinforcement
of site boundary embankment
should be provided immediately to prevent further overflow (Portion I opposite to site office) |
Sandbag
with cement motar and water pump were provided to prevent overflow. |
Completion as observed on 30 Jan 2013 |
130123_03 |
23-Jan-13 |
Muddy water and muddy trail at site exit should be cleared ( |
Muddy trail at exit has been cleared |
Completion as observed on 30 Jan 2013 |
8.0.5.
Four site inspections for Contract no.
HK/2009/01 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.3
Table 8.3 Summary of Environmental Inspections
for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
130102_01 |
2-Jan-13 |
Dusty trail was observed on the public road which should be cleaned
up and the vehicle wheels should be washed completely when they exit the
site. (Opposite to Grand Hyatt) |
The dusty trail was cleaned. |
Completion as observed on 9-Jan-13 |
130102_02 |
2-Jan-13 |
The chemical containers should be provided with drip tray. (Children's
playground) |
The chemical containers were removed. |
Completion as observed on 9-Jan-13 |
130109_01 |
9-Jan-13 |
The muddy trail was observed on the public road which should be
cleaned up. (Water Channel) |
The muddy trail was cleaned up. |
Completion as observed on 17-Jan-13 |
130117_01 |
17-Jan-13 |
Chemical container was placed directly under sun shine without
drip tray. Drip tray should be provided for chemical container.(Children's
playground) |
The chemical
container was removed |
Completion as observed on 23-Jan-13 |
130117_02 |
17-Jan-13 |
Filling material at barge should be cleaned and removed to
prevent direct dropping of material into sea.( |
The filling material was cleaned up |
Completion as observed on 23-Jan-13 |
130123_01 |
23-Jan-13 |
Oil stain on the bare ground should be cleared up as chemical
waste(B42)(Water Channel)
|
Oil stain was removed. |
Completion as observed on 30 Jan 13 |
130123_02 |
23-Jan-13 |
Oil drum should be cleared and removed or drip tray should be
provided.(B42) |
Oil drum have been removed |
Completion as observed on 30 Jan 13 |
130123_03 |
23-Jan-13 |
Noise barrier should be proper maintained and repaired |
Noise barrier was repaired |
Completion as observed on 30 Jan 13 |
8.0.6.
Four site inspections for Contract no.
HK/2009/02 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.4
Table 8.4 Summary of Environmental Inspections
for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
130103_01 |
3-Jan-13 |
Overflow of muddy water from wheel washing facility to the public
road was observed. The adequacy of the volume of the washing facility should
be reviewed and all wastewater should be treated before discharge. (WCR1) |
The condition of wheel washing facility was improved |
Completion
as observed on 10-Jan-13 |
130103_02 |
3-Jan-13 |
Tarpaulin sheet should be provided for the transfer of sediment
to the barge (WCR1) |
The barge was removed. |
Completion
as observed on 10-Jan-13 |
130110_01 |
10-Jan-13 |
The floating debris should be removed more regularly (Eastern
temporary seawall) |
Floating debris was collected. |
Completion
as observed on 16-Jan-13 |
8.0.7.
No site inspections for Contract no.
HY/2009/17 were carried out during this reporting period1. Construction of bored pile E3B under
HY/2009/17 was confirmed completed and the respective work area under FEP was
inspected under HY/2009/19 from 19 Dec 2012 onwards.
8.0.8.
Four site inspections for Contract no.
HK/2010/06 was carried out during this reporting period. The results of these
inspections and outcomes are summarized in Table 8.5
Table 8.5 Summary of Environmental Inspections
for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
130107_01 |
7-Jan-12 |
The oil stain was observed on the platform which should be
cleaned and removed as chemical waste |
The oil stain was removed |
Completion as observed on 17-Jan-13 |
130117_01 |
17-Jan-12 |
Some abandon oil drums were observed, which should be cleaned and
removed( section II) |
The oil drums were removed |
Completion as observed on 21-Jan-13 |
130121_01 |
21-Jan-12 |
Oil stain was observed on the ground which should be cleaned and
removed as chemical waste(section II) |
The oil stain was cleaned and removed |
Completion as observed on 28-Jan-13 |
9.0.1. No
environmental complaint was received in the reporting period.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on
Complaints
Reporting Period |
No. of Complaints |
Jan 2013 |
0 |
Sep 2010 ¡V Dec 2012 |
20 |
Total |
20 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1. The construction
programmes of individual contracts are provided in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of
Individual Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HY/2009/15 |
¡P
ELS works at TS4 ¡P
Rock breaking works at TPCWAE ¡P
Tunnel works at TS1 ¡P
Horizontal drilling for mined tunnel ¡P
Pipe roofing installation ¡P
Construction of Diaphragm Wall at TS2 |
¡P
Watering any dust generating activities ¡P
Checking all drip trays frequently and clear any stagnant water and
mud inside it. ¡P
Noise control measures shall be provided during restricted hours |
HY/2009/17 |
¡P
No further works under designated project |
¡P
N/A |
HY/2009/18 |
¡P
Excavation of trial pit ¡P
Transplanting of trees ¡P
Hoarding erection and modification ¡P
Installation of couplers, UU detection, trial trench, pre-drilling ¡P
Excavation ¡P
Sheet Piling ¡P
Drainage works ¡P
Tunnel works ¡P
Trough structure construction and associated drilling and grouting ¡P
Road works ¡P
OHVD installation ¡P
Cooling main bridge construction ¡P
Pre-bored H-piling ¡P
Bridge construction |
¡P
Noise barrier shall be implemented; and ¡P
Noise level shall be controlled by reducing piling rate and no. of
plants working in parallel. ¡P
Dust control during dust generating activities ¡P
Provide protection works to ensure no runoff out of site area or
direct discharge into public drainage system. ¡P
Appropriate plants and measures should be taken to ensure adequate
protections are provided for trees being transplanted. |
HY2009/19 |
¡P
Road works at ¡P
Bored piling (Land) ¡P
Pre-drilling works for bored pile and Diaphragm wall ¡P
D-wall Construction (North & South Section) ¡P
Guide wall construction for D-wall / Barrette at North side ¡P
Construction works for Box Culvert T1 ¡P
Marine Piling ¡P
Construct ion of socket-H pile ¡P
Construction works for Culvert U1 ¡P
Construction of Pile caps & columns (Land) ¡P
Dismantling of marine platform ¡P
Demolition of parapet at IEC Link ¡P
Construction of Pile caps & columns (Marine) ¡P
Cut & Cover Tunnel sheet piling works and installation of King
Pos ¡P
Construction of dewatering well for Cut & Cover Tunnel |
¡P
Noise level shall be controlled by reducing the pilling operation
rate. ¡P
Noise barrier shall be implemented. ¡P
Dust control during dust generating works ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. |
HK2009/01 |
¡P
Removal of remaining guide wall along ¡P
Backfilling at SCL section to the required level. ¡P
Installation of pre-bored H-pile in CWB Stage 1b (from Ch80 to Ch120). ¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220). ¡P
CWB diaphragm wall construction under the atrium link. |
¡P
Noise level shall be controlled by reducing no. of plants working in
parallel. ¡P
Well maintained enclosures for grouting mixing plants. ¡P
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. ¡P
Dust control during dust generating works |
HK/2009/02 |
¡P
Blinding for the base slab construction and waterproofing
installation at tunnel portion 1. ¡P
Rebar fixing fro the base slab construction at Tunnel Portion 1. ¡P
Base slab concreting at Tunnel Portion 1. ¡P
G.I. and remove the temporary sheetpile wall at WCR2 ¡P
Diaphragm wall construction for Eastern Bulkhead Panel BHP3 and BHP7. ¡P
Bulkhead at Bay 14 of Box Culvert ¡§O¡¨ and stage 2 diversion of uncharted
drainage works at Box culvert ¡§O¡¨. ¡P
Preparation work for Bored Pile construction of EP01 ¡V EP11 at Tunnel Portion 3&4. ¡P
Trial excavation, footpath set back, UU diversion, reprovision of
street furniture and preparation works for Hung Hing Road Diversion Stage 1 ¡P
Curing of caisson seawall precast unit 2X and protective coating on
flat-top barge. ¡P
Construction of 1800 connection of Box Culvert N1, Bay 4 & Bay 5
and FRP installation at WCR1 area. |
¡P
Dust control during dust generating works ¡P
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HK/2010/06 |
¡P
Utility works in section 2 |
¡P
Air pollution control during transportation |
10.0.3. The
construction works of Contract no. 04/HY/2006 ¡V Reconstruction of Bus Terminus
near